|
|
DAR File No. 28803 |
| This filing was published in the 07/01/2006, issue, Vol. 2006, No. 13, of the Utah State Bulletin. |
| [ 07/01/2006 Bulletin Table of Contents / Bulletin Page ] |
|
Public Service Commission, Administration R746-345 Pole Attachments
|
NOTICE OF PROPOSED RULE |
|
DAR File No.: 28803
|
RULE ANALYSIS |
Purpose of the rule or reason for the change: |
|
Comments submitted in May 2006 in another rule amendment proceeding established that industry practice is that individual owners of facilities involved with pole attachments perform make-ready work for their own facilities and this work is coordinated by the pole owner. A new definition is proposed to be added to the rule to reflect this industry practice. The other proposed change to the rule seeks to follow this industry practice and clarifies that each facility owner may continue to perform the make-ready work or may reach other agreements on how such make-ready work is performed by others. The rule is also clarified to ensure that where a self-build option is available, necessary cost information is made available to the new attaching entity in order to make an informed selection of a self-build option. An additional provision is added clarifying that an applicant may reject a make-ready estimate or make-ready construction time-line if the applicant believes that they are not prepared in good faith, are not reasonable, or otherwise not in the public interest. The Commission will resolve these disputes.
|
Summary of the rule or change: |
|
A new definition for "make-ready work" is added to the definitions and the definitions are rearranged alphabetically. Provisions of Section R746-345-3 dealing with information regarding make-ready work costs and construction periods are amended to clarify that information will be provided for each facility owner's make-ready work, as well as information on the availability of and conditions for a self-build option, if available.
|
State statutory or constitutional authorization for this rule: |
|
Sections 54-3-1, 54-3-13, and 54-4-1; and 47 U.S.C. 224(c)
|
Anticipated cost or savings to: |
the state budget: |
|
None--The changes will cause no change in state agencies' activities. While the rule clarifies that disputes concerning make-ready work may be brought to the Commission, the Commission already deals with similar disputes and will accommodate these disputes within its existing operations.
|
local governments: |
|
None--The proposed rule changes will have no effect on local government's activities under the rule beyond providing them with more detailed information on the self-build options that may be available.
|
other persons: |
|
None--The rule attempts to follow industry practice and as such, no changes are anticipated in their activities as a result of the proposed changes. The proposed changes make available more detailed information on the self-build options that may be available.
|
Compliance costs for affected persons: |
|
As the rule follows industry practice, the Commission does not anticipate that there will be any compliance costs with the rule. The changes simply provide greater clarity on how the existing rule's requirement for the dissemination of information is to be done.
|
Comments by the department head on the fiscal impact the rule may have on businesses: |
|
Comments received from the last rule change proposal provided information regarding industry practice on how make-ready work is preformed and coordinated. The Commission anticipates that there will be no fiscal impact on businesses as the rule follows current industry practices. Ric Campbell, Chairman
|
The full text of this rule may be inspected, during regular business hours, at the Division of Administrative Rules, or at: |
|
Public Service Commission Administration HEBER M WELLS BLDG 160 E 300 S SALT LAKE CITY UT 84111-2316
|
Direct questions regarding this rule to: |
|
Barbara Stroud or Sandy Mooy at the above address, by phone at 801-530-6714 or 801-530-6708, by FAX at 801-530-6796 or 801-530-6796, or by Internet E-mail at bstroud@utah.gov or smooy@utah.gov
|
Interested persons may present their views on this rule by submitting written comments to the address above no later than 5:00 p.m. on: |
|
08/01/2006
|
This rule may become effective on: |
|
08/09/2006
|
Authorized by: |
|
Sandy Mooy, Legal Counsel
|
RULE TEXT |
|
R746. Public Service Commission, Administration. R746-345. Pole Attachments. R746-345-2. General Definitions. A. "Attaching Entity" -- A public utility, wireless provider, cable television company, communications company, or other entity that provides information or telecommunications services that attaches to a pole owned or controlled by a public utility. B. [ C. [ D. [ E. [ [ G. [ H. [ I. "Wireless Provider" -- A corporation, partnership, or firm that provides cellular, Personal Communications Systems (PCS), or other commercial mobile radio service as defined in 47 U.S.C. 332 that has been issued a covering license by the Federal Communications Commission.
R746-345-3. Tariffs and Contracts. A. Tariff Filings and Standard Contracts -- A pole owner shall submit a tariff and standard contract, or a Statement of Generally Available Terms (SGAT), specifying the rates, terms and conditions for any pole attachment, to the Commission for approval. 1. A pole owner must petition the Commission for any changes or modifications to the rates, terms, or conditions of its tariff, standard contract or SGAT. A petition for change or modification must include a showing why the rate, term or condition is no longer just and reasonable. A change in rates, terms or conditions of an approved tariff, standard contract or SGAT will not become effective unless and until it has been approved by the Commission. 2. The tariff, standard contract or SGAT shall identify all rates, fees, and charges applicable to any pole attachment. The tariff, standard contract, and SGAT shall also include: a. a description of the permitting process, the inspection process, the joint audit process, including shared scheduling and costs, and any non-recurring fee or charge applicable thereto; b. emergency access provisions; and c. any back rent recovery or unauthorized pole attachment fee and any applicable procedures for determining the liability of an attaching entity to pay back rent or any non-recurring fee or charge applicable thereto. B. Establishing the Pole Attachment Relationship -- The pole attachment relationship shall be established when the pole owner and the attaching entity have executed the approved standard contract, or SGAT, or other Commission-approved contract. 1. Exception -- The pole owner and attaching entity may voluntarily negotiate an alternative contract incorporating some, all, or none of the terms of the standard contract or SGAT. The parties shall submit the negotiated contract to the Commission for approval. In situations in which the pole owner and attaching entity are unable to agree following good faith negotiations, the pole owner or attaching entity may petition the Commission for resolution as provided in Section R746-345-6. Pending resolution by the Commission, the parties shall use the standard contract or SGAT. C. Make-Ready Work, Timeline and Cost Methodology -- As a part of the application process, the pole owner shall provide the applicant with an estimate of the cost of the make-ready work required and the expected time to complete the make-ready work as provided for in this sub-section. All applications by a potential attacher within a given calendar month shall be counted as a single application for the purposes of calculating the response time to complete the make-ready estimate for the pole owner. The due date for a response to all applications within the calendar month shall be calculated from the date of the last application during that month. As an alternative to all of the time periods allowed for construction below, a pole owner may provide the applicant with an estimated time by which the work could be completed that is different than the standard time periods contained in this rule with an explanation for the anticipated delay. Pole owners must provide this alternative estimate within the estimate timelines provided below. Applicants that wish to consider self-building shall inform the pole owner at the time of application that they are considering the self-build option, if available, and they would like a two-alternative make-ready bid. The pole owner and each existing attaching entity are responsible to determine what portion, if any, of the make-ready work their facilities require which may be performed through a self-build option and what conditions, if any, are associated with such self-build option. In the first alternative, the pole owner and attaching entities would be responsible for all necessary make-ready work. For the second alternative, the pole owner and attaching entities will identify what make-ready work they will perform, if any, with an associated cost estimate, and also identify what make-ready work, if any, the owner is agreeable to have performed through a self-build option and the conditions, if any, for such self-build option. 1. For applications up to 20 poles, the pole owner shall respond with either an approval or a rejection within 45 days. At the same time as an approval is given, a completed make-ready estimate must be provided to the applicant explaining what make-ready work must be done, the cost of that work, and the time by which the work would be finished, that is no later than 120 days from receiving an initial deposit payment for the make-ready work. 2. For applications that represent greater than 20 poles, but equal to or less than .5% of the pole owner's poles in Utah, or 300 poles, whichever is lower, the time for the pole owner's approval and make-ready estimate shall be extended to 60 days, and the time for construction will remain at a maximum of 120 days. 3. For applications that represent greater than the number of poles calculated in section 3(2)(C)(2) above, but equal to or less than 5% of the pole owner's poles in Utah, or 3,000 poles, whichever is lower, the time for the approval and make-ready estimate shall be extended to 90 days, and the time for construction will be extended to 180 days. 4. For applications that represent greater than 5% of the pole owner's poles in Utah, or 3,000 poles, whichever is lower, the times for the above activities will be negotiated in good faith. The pole owner shall, within 20 days of the application, inform the applicant of the date by which the pole owner will have the make-ready estimate and make-ready construction time lines prepared for the applicant. If the applicant believes the pole owner is not acting in good faith, it may appeal to the Commission to either resolve the issue of when the make-ready estimate and construction period information should be delivered or to arbitrate the negotiations. 5. If the pole owner rejects any application, the pole owner must state the specific reasons for doing so. Applicants may appeal to the Commission if they do not agree that the pole owner's stated reasons are sufficient grounds for rejection. 6. For all
approved applications, the applicant will either accept or reject the
make-ready estimate. If it accepts the
make-ready estimate and make-ready construction time line, the work must be
done [ 7. Applicants must pay 50% of the make-ready estimate in advance of construction, and pay the remainder in two subsequent installment payments: an additional 25 percent payment when half of the work is done and the balance after the work is completed. Applicants may elect to pay the entire amount up front. 8. [ 9. An applicant may reject a make-ready estimate if it wishes to contest, before the Commission, that the make-ready estimate or make-ready construction time line is not prepared in good-faith, or is unreasonable or not in the public interest. D. Pole Attachment Placement -- All new copper cable attachments shall be placed at the lowest level permitted by applicable safety codes. In cases where an existing copper attachment has been placed in a location higher than the minimum height the safety codes require, the pole owner shall determine if the proposed attachment may be safely attached either above or below the existing copper attachment taking account of midspan clearances and potential crossovers. If these attachment locations, above or below the copper cable, comply with the applicable safety code, the attacher may attach to the pole without paying to move the copper cable. The owner of the copper cable may elect to pay the costs of having the cable moved to the lowest position as part of the attachment process, or it may elect to move the cable themselves prior to the attaching entity's attachment. If the copper cable must be moved in order for the attacher to be able to safely make its attachment, the attacher shall pay the costs associated with moving the existing copper cable.
KEY: public utilities, rules and procedures, telecommunications, telephone utility regulation Date of
Enactment or Last Substantive Amendment:
[ Notice of Continuation: August 8, 2003 Authorizing, and Implemented or Interpreted Law: 54-4-13
|
ADDITIONAL INFORMATION |
|
PLEASE NOTE:
|
|
For questions regarding the content or application of this rule, please contact Barbara Stroud or Sandy Mooy at the above address, by phone at 801-530-6714 or 801-530-6708, by FAX at 801-530-6796 or 801-530-6796, or by Internet E-mail at bstroud@utah.gov or smooy@utah.gov For questions about the rulemaking process, please contact the Division of Administrative Rules (801-538-3764). Please Note: The Division of Administrative Rules is NOT able to answer questions about the content or application of these administrative rules. |
| [ 07/01/2006 Bulletin Table of Contents / Bulletin Page ] |
| Last modified: 07/03/2006 2:52 PM |