Rule R277-454. Construction Management of School Building Projects.
As in effect on August 1, 2009
Table of Contents
- R277-454-1. Definitions.
- R277-454-2. Authority and Purpose.
- R277-454-3. Standards.
- KEY
- Date of Enactment or Last Substantive Amendment
- Notice of Continuation
- Authorizing, Implemented, or Interpreted Law
R277-454-1. Definitions.
A. "Board" means the Utah State Board of Education.
B. "CM" means an individual designated as a construction manager. The CM may be an architect, engineer, general contractor, or other professional consultant. It may also be an entity which is referred to as a construction management firm. The CM works as the agent of the owner of the construction project. The CM, at the discretion of the owner, may assist in the development and implementation of any or all of the predesign, design, bidding, construction, and occupancy stages of the construction project. The CM is responsible for the effective, orderly, and acceptable completion of the construction project.
C. "Construction management" means a contractual and professional working relationship between the owner of a construction project and a CM.
R277-454-2. Authority and Purpose.
A. This rule is authorized by Article X, Section 3 of the Utah Constitution which vests general control and supervision of public education in the Board, Section 53A-1-401(3) which allows the Board to adopt rules in accordance with its responsibilities and Section 53A-20-103 which requires the Board to prepare an annual school plant capital outlay report of all school districts, which includes information on the number and size of building projects completed and under construction.
B. The purpose of this rule is to specify the standards local boards of education shall follow in using construction management for school construction projects.
R277-454-3. Standards.
A. A construction management contract shall clearly specify the duties of the CM with respect to the building project.
B. A local school district shall bid each component part of the building project in accordance with advertising, public opening, performance bond, payment bond, and other statutory requirements.
KEY
educational facilities, education finance
Date of Enactment or Last Substantive Amendment
August 15, 2003
Notice of Continuation
October 5, 2007
Authorizing, Implemented, or Interpreted Law
Art X Sec 3; 53A-1-401(3); 53A-20-103
Rule converted into HTML by the Division of Administrative Rules.
For questions regarding the content or application of rules under Title R277, please contact the promulgating agency (Education, Administration). A list of agencies with links to their homepages is available at http://www.utah.gov/government/agencylist.html or from http://www.rules.utah.gov/contact/agencycontacts.htm.
For questions about the rulemaking process, please contact the Division of Administrative Rules (801-538-3764). Please Note: The Division of Administrative Rules is not able to answer questions about the content or application of these rules.
The HTML version of this rule is a convenience copy made available on the Internet as a public service. Please see the State of Utah Terms of Use.