The rules in R645-300-100 present the procedures to carry out the entitled activities.

110. Introduction.

111. Objectives. The objectives of R645-300-100 are to:

111.100. Provide for broad and effective public participation in the review of applications and the issuance or denial of permits;

111.200. Ensure prompt and effective review of each permit application by the Division; and

111.300. Provide the requirements for the terms and conditions of permits issued and the criteria for approval or denial of a permit.

112. Responsibilities.

112.100. The Division has the responsibility to approve or disapprove permits under the approved State Program.

112.200. The Division and persons applying for permits under the State Program will involve the public throughout the permit process of the State Program.

112.300. The Division will assure implementation of the requirements of R645-300 under the State Program.

112.400. All persons who engage in and carry out any coal mining and reclamation operations will first obtain a permit from the Division. The applicant will provide all information in an administratively complete application for review by the Division in accordance with R645-300 and the State Program.

112.500. Any permittee seeking to renew a permit for coal mining and reclamation operations solely for the purpose of reclamation and not for the further extraction, processing, or handling of the coal resource will follow the procedures set forth in R645-303-232.500.

113. Coordination with requirements under other laws. The Division will provide for the coordination of review and issuance of permits for coal mining and reclamation operations with applicable requirements of the Endangered Species Act of 1973, as amended (16 U.S.C. 1531 et seq.); the Fish and Wildlife Coordination Act, as amended (16 U.S.C. 661 et seq.); the Migratory Bird Treaty Act of 1918, as amended (16 U.S.C. 703 et seq.); The National Historic Preservation Act of 1966, as amended (16 U.S.C. 470 et seq.); the Bald Eagle Protection Act, as amended 16 U.S.C. 668a); and where federal and Indian lands covered by that Act are involved, the Archeological and Historic Preservation Act of 1974 (16 U.S.C. 469 et seq.); and the Archaeological Resources Protection Act of 1979 (16 U.S.C. 470aa et seq.).

120. Public Participation in Permit Processing.

121. Filing and Public Notice.

121.100. Upon submission of an administratively complete application, an applicant for a permit, significant revision of a permit under R645-303-220 or renewal of a permit under R645-303-230 will place an advertisement in a local newspaper of general circulation in the locality of the proposed coal mining and reclamation operation at least once a week for four consecutive weeks. A copy of the advertisement as it will appear in the newspaper will be submitted to the Division. The advertisement will contain, at a minimum, the following:

121.110. The name and business address of the applicant;

121.120. A map or description which clearly shows or describes the precise location and boundaries of the proposed permit area and is sufficient to enable local residents to readily identify the proposed permit area. It may include towns, bodies of water, local landmarks, and any other information which would identify the location. If a map is used, it will indicate the north direction;

121.130. The location where a copy of the application is available for public inspection;

121.140. The name and address of the Division, where written comments, objections, or requests for informal conferences on the application may be submitted under R645-300-122 and R645-300-123;

121.150. If an applicant seeks a permit to mine within 100 feet of the outside right-of-way of a public road or to relocate or close a public road, except where public notice and hearing have previously been provided for this particular part of the road in accordance with R645-103-234; a concise statement describing the public road, the particular part to be relocated or closed, and the approximate timing and duration of the relocation or closing; and

121.160. If the application includes a request for an experimental practice under R645-302-210, a statement indicating that an experimental practice is requested and identifying the regulatory provisions for which a variance is requested.

121.200. The applicant will make an application for a permit, significant revision under R645-303- 220, or renewal of a permit under R645-303-230 available for the public to inspect and copy by filing a full copy of the application with the recorder at the courthouse of the county where the coal mining and reclamation operation is proposed to occur, or an accessible public office approved by the Division. This copy of the application need not include confidential information exempt from disclosure under R645-300-124. The application required by R645-300-121 will be filed by the first date of newspaper advertisement of the application. The applicant will file any changes to the application with the public office at the same time the change is submitted to the Division.

121.300. Upon receipt of an administratively complete application for a permit, a significant revision to a permit under R645-303-220, or a renewal of a permit under R645-303-230, the Division will issue written notification indicating the applicant's intention to conduct coal mining and reclamation operations within the described tract of land, the application number or other identifier, the location where the copy of the application may be inspected, and the location where comments on the application may be submitted. The notification will be sent to:

121.310. Local governmental agencies with jurisdiction over or an interest in the area of the proposed coal mining and reclamation operation, including but not limited to planning agencies, sewage and water treatment authorities, water companies; and

121.320. All federal or state governmental agencies with authority to issue permits and licenses applicable to the proposed coal mining and reclamation operation and which are part of the permit coordinating process developed in accordance with the State Program, Section 503(a)(6) or Section 504(h) of P.L. 95-87, or 30 CFR 733.12; or those agencies with an interest in the proposed coal mining and reclamation operation, including the U.S. Department of Agriculture Soil Conservation Service district office, the local U.S. Army Corps of Engineers district engineer, the National Park Service, state and federal fish and wildlife agencies, and Utah State Historic Preservation Officer.

122. Comments and Objections on Permit Application.

122.100. Within 30 days of the last newspaper publication, written comments or objections to an application for a permit, significant revision to a permit under R645-303-220, or renewal of a permit under R645-303-230 may be submitted to the Division by public entities notified under R645-300-121.300 with respect to the effects of the proposed coal mining and reclamation operation on the environment within their areas of responsibility.

122.200. Written objections to an application for a permit, significant revision to a permit under R645-303-220, or renewal of a permit under R645-303-230 may be submitted to the Division by any person having an interest which is or may be adversely affected by the decision on the application, or by an officer or head of any federal, state, or local government agency or authority, within 30 days after the last publication of the newspaper notice required by R645- 300-121.

122.300. The Division will upon receipt of such written comments or objections:

122.310. Transmit a copy of the comments or objections to the applicants; and

122.320. File a copy for public inspection at the Division.

123. Informal Conferences.

123.100. Any person having an interest which is or may be adversely affected by the decision on the application, or an office or a head of a federal, state, or local government agency, may request in writing that the Division hold an informal conference on the application for a permit, significant revision to a permit under R645-303-220, or renewal of a permit under R645-303-230. The request will:

123.110. Briefly summarize the issues to be raised by the requestor at the conference;

123.120. State whether the requestor desires to have the conference conducted in the locality of the proposed coal mining and reclamation operation; and

123.130. Be filed with the Division no later than 30 days after the last publication of the newspaper advertisement required under R645-300-121.

123.200. Except as provided in R645-300-123.300, if an informal conference is requested in accordance with R645-300-123.100, the Division will hold an informal conference within 30 days following the receipt of the request. The informal conference will be conducted as follows:

123.210. If requested under R645-300-123.120, it will be held in the locality of the proposed coal mining and reclamation operation.

123.220. The date, time, and location of the informal conference will be sent to the applicant and other parties to the conference and advertised by the Division in a newspaper of general circulation in the locality of the proposed coal mining and reclamation operation at least two weeks before the scheduled conference.

123.230. If requested in writing by a conference requestor at a reasonable time before the conference, the Division may arrange with the applicant to grant parties to the conference access to the proposed permit area and, to the extent that the applicant has the right to grant access to it, to the adjacent area prior to the established date of the conference for the purpose of gathering information relevant to the conference.

123.240. The requirements of the Procedural Rules of the Board of Oil, Gas and Mining (R641 Rules) will apply to the conduct of the informal conference. The conference will be conducted by a representative of the Division, who may accept oral or written statements and any other relevant information from any party to the conference. An electronic or stenographic record will be made of the conference, unless waived by all the parties. The record will be maintained and will be accessible to the parties of the conference until final release of the applicant's performance bond or other equivalent guarantee pursuant to R645-301-800.

123.300. If all parties requesting the informal conference withdrew their request before the conference is held, the informal conference may be canceled.

123.400. An informal conference held in accordance with R645-300-123 may be used by the Division as the public hearing required under R645-103-234 on proposed relocation or closing of public roads.

124. Public Availability of Permit Applications.

124.100. General Availability. Except as provided in R645-300-124.200 and R645-300-124.300, all applications for permits; permit changes; permit renewals; and transfers, assignments or sales of permit rights on file with the Division will be made available, at reasonable times, for public inspection and copying.

124.200. Limited Availability. Except as provided in R645-300-124.310, information pertaining to coal seams, test borings, core samplings, or soil samples in an application will be made available to any person with an interest which is or may be adversely affected. Information subject to R645-300-124 will be made available to the public when such information is required to be on public file pursuant to Utah law.

124.300. Confidentiality. The Division will provide procedures, including notice and opportunity to be heard for persons both seeking and opposing disclosure, to ensure confidentiality of qualified confidential information, which will be clearly identified by the applicant and submitted separately from the remainder of the application. Confidential information is limited to:

124.310. Information that pertains only to the analysis of the chemical and physical properties of the coal to be mined, except information on components of such coal which are potentially toxic in the environment.

124.320. Information required under section 40-10-10 of the Act that is authorized by that section to be held confidential and is not on public file pursuant to Utah law and that the applicant has requested in writing to be held confidential; and

124.330. Information on the nature and location of archeological resources on public land and Indian land as required under the Archeological Resources Protection Act of 1979 (P. L. 96-95, 93 Stat. 721, 16 U.S.C. 470).

130. Review of Permit Application.

131. General.

131.100. The Division will review the application for a permit, permit change, or permit renewal; written comments and objections submitted; and records of any informal conference or hearing held on the application and issue a written decision, within a reasonable time set by the Division, either granting, requiring modification of, or denying the application. If an informal conference is held under R645-300-123 the decision will be made within 60 days of the close of the conference, unless a later time is necessary to provide an opportunity for a hearing under R645-300- 210.

131.110. Application review will not exceed the following time periods:

131.111. Permit change applications.

131.111.1. Significant revision - 120 days.

131.111.2. Amendments - 60 days.

131.112. Permit renewal - 120 days.

131.113. New underground mine applications - One year.

131.114. New surface mine applications - One year.

131.120. Time will be counted as cumulative days of Division review and will not include operator response time or time delays attributed to informal or formal conferences or Board hearings.

131.200. The applicant for a permit or permit change will have the burden of establishing that their application is in compliance with all the requirements of the State Program.

131.300. If, after review of the application for a permit, permit change, or permit renewal, additional information is required, the Division will issue a written finding providing justification as to why the additional information is necessary to satisfy the requirements of the R645 Rules and issue a written decision requiring the submission of the information.

132. Review of Compliance.

132.100. The Division will review available information on state and federal failure-to-abate cessation orders, unabated federal and state imminent harm cessation orders, delinquent civil penalties issued under section 518 of the federal Act, SMCRA-derived laws of other states, and section 40-10-20 of the Act, bond forfeitures where violations on which the forfeitures are based have not been corrected, delinquent abandoned mine reclamation fees, and unabated violations of the Act, derivative laws of other states and federal air and water protection laws, rules and regulations incurred at any coal mining and reclamation operations connected with the applicant. The Division will then make a finding that neither the applicant, nor any person who owns or controls the applicant, nor any person owned or controlled by the applicant is currently in violation of any law, rule, or regulation referred to in R645-300-132. If such a finding cannot be made, the Division will require the applicant, before issuance of the permit, to either:

132.110. Submit to the Division proof that the current violation has been or is in the process of being corrected to the satisfaction of the agency that has jurisdiction over the violation; or

132.120. Establish for the Division that the applicant or any person owned or controlled by the applicant or any person who owns or controls the applicant has filed and is presently pursuing, in good faith, a direct administrative or judicial appeal to contest the validity of the current violation. If the initial judicial review authority under R645-300-220 either denies a stay applied for in the appeal or affirms the violation, then the applicant will within 30 days submit the proof required under R645-300-132.110.

132.200. Any permit that is issued on the basis of proof submitted under R645-300-132.110 or pending the outcome of an appeal described in R645-300-132.120 will be issued conditionally.

132.300. If the Division makes a finding that the applicant, or anyone who owns or controls the applicant, or the operator specified in the application, controls or has controlled coal mining and reclamation operations with a demonstrated pattern of willful violations of the Act of such nature and duration and with such resulting irreparable damage to the environment as to indicate an intent not to comply with the Act, the application will not be granted. Before such a finding becomes final, the applicant or operator will be afforded an opportunity for an adjudicatory hearing on the determination as provided for in R645-300-210.

133. Written Findings for Permit Application Approval. No permit application or application for a permit change will be approved unless the application affirmatively demonstrates and the Division finds, in writing, on the basis of information set forth in the application or from information otherwise available that is documented in the approval, the following:

133.100. The application is complete and accurate and the applicant has complied with all the requirements of the State Program;

133.200. The proposed permit area is:

133.210. Not within an area under study or administrative proceedings under a petition, filed pursuant to R645-103-400 or 30 CFR 769, to have an area designated as unsuitable for coal mining and reclamation operations, unless the applicant demonstrates that before January 4, 1977, substantial legal and financial commitments were made in relation to the operation covered by the permit application; or

133.220. Not within an area designated as unsuitable for mining pursuant to R645-103-300 and R645- 103-400 or 30 CFR 769 or subject to the prohibitions or limitations of R645-103-230;

133.300. For coal mining and reclamation operations where the private mineral estate to be mined has been severed from the private surface estate, the applicant has submitted to the Division the documentation required under R645-301-114.200;

133.400. The Division has made an assessment of the probable cumulative impacts of all anticipated coal mining and reclamation operations on the hydrologic balance in the cumulative impact area and has determined that the proposed operation has been designed to prevent material damage to the hydrologic balance outside the permit area;

133.500. The operation would not affect the continued existence of endangered or threatened species or result in destruction or adverse modification of their critical habitats, as determined under the Endangered Species Act of 1973 (16 U.S.C. 1531 et.seq.);

133.600. The Division has taken into account the effect of the proposed permitting action on properties listed on and eligible for listing on the National Register of Historic Places. This finding may be supported in part by inclusion of appropriate permit conditions or changes in the operation plan protecting historic resources, or a documented decision that the Division has determined that no additional protection measures are necessary; and

133.700. The applicant has:

133.710. Demonstrated that reclamation as required by the State Program can be accomplished according to information given in the permit application.

133.720. Demonstrated that any existing structure will comply with the applicable performance standards of R645-301 and R645-302.

133.730. Paid all reclamation fees from previous and existing coal mining and reclamation operations as required by 30 CFR Part 870.

133.740. Satisfied the applicable requirements of R645-302.

133.750. If applicable, satisfied the requirements for approval of a long-term, intensive agricultural postmining land use, in accordance with the requirements of R645-301-353.400.

133.800. For a proposed remining operation where the applicant intends to reclaim in accordance with the requirements of R645-301-553.500, the site of the operation is a previously mined area as defined in R645-100-200.

134. Performance Bond Submittal. If the Division decides to approve the application, it will require that the applicant file the performance bond or provide other equivalent guarantee before the permit is issued, in accordance with the provisions of R645-301-800.

140. Permit Conditions. Each permit issued by the Division will be subject to the following conditions:

141. The permittee will conduct coal mining and reclamation operations only on those lands that are specifically designated as the permit area on the maps submitted with the application and authorized for the term of the permit and that are subject to the performance bond or other equivalent guarantee in effect pursuant to R645-301-800.

142. The permittee will conduct all coal mining and reclamation operations only as described in the approved application, except to the extent that the Division otherwise directs in the permit.

143. The permittee will comply with the terms and conditions of the permit, all applicable performance standards and requirements of the State Program.

144. Without advance notice, delay, or a search warrant, upon presentation of appropriate credentials, the permittee will allow the authorized representatives of the Division to:

144.100. Have the right of entry provided for in R645-400-110 and R645-400-220.

144.200. Be accompanied by private persons for the purpose of conducting an inspection in accordance with R645-400-100 and R645-400-200 when the inspection is in response to an alleged violation reported to the Division by the private person.

145. The permittee will take all possible steps to minimize any adverse impact to the environment or public health and safety resulting from noncompliance with any term or condition of the permit, including, but not limited to:

145.100. Any accelerated or additional monitoring necessary to determine the nature and extent of noncompliance and the results of the noncompliance;

145.200. Immediate implementation of measures necessary to comply; and

145.300. Warning, as soon as possible after learning of such noncompliance, any person whose health and safety is in imminent danger due to the noncompliance.

146. As applicable, the permittee will comply with R645-301 and R645-302 for compliance, modification, or abandonment of existing structures.

147. The operator will pay all reclamation fees required by 30 CFR Part 870 for coal produced under the permit, for sale, transfer or use.

148. Within 30 days after a cessation order is issued under R645-400-310, except where a stay of the cessation order is granted and remains in effect, the permittee will either submit the following information current to when the order was issued or inform the Division in writing that there has been no change since the immediately preceding submittal of such information:

148.100. Any new information needed to correct or update the information previously submitted to the Division by the permittee under R645-301-112.300.

148.200. If not previously submitted, the information required from a permit applicant by R645-301- 112.300.

150. Permit Issuance and Right of Renewal.

151. Decision. If the application is approved, the permit will be issued upon submittal of a performance bond in accordance with R645-301-800. If the application is disapproved, specific reasons therefore will be set forth in the notification required by R645-300-152.

152. Notification. The Division will issue written notification of the decision to the following persons and entities:

152.100. The applicant, each person who files comments or objections to the permit application, and each party to an informal conference;

152.200. The local governmental officials in the local political subdivision in which the land to be affected is located within 10 days after the issuance of a permit, including a description of the location of the land; and

152.300. The Office.

153. Permit Term. Each permit will be issued for a fixed term of five years or less, unless the requirements of R645-301-116 are met.

154. Right of Renewal. Permit application approval will apply to those lands that are specifically designated as the permit area on the maps submitted with the application and for which the application is complete and accurate. Any valid permit issued in accordance with R645-300-151 will carry with it the right of successive renewal, within the approved boundaries of the existing permit, upon expiration of the term of the permit, in accordance with R645- 303-230.

155. Initiation of Operations.

155.100. A permit will terminate if the permittee has not begun the coal mining and reclamation operation covered by the permit within three years of the issuance of the permit.

155.200. The Division may grant a reasonable extension of time for commencement of these operations, upon receipt of a written statement showing that such an extension of time is necessary, if:

155.210. Litigation precludes the commencement or threatens substantial economic loss to the permittee; or

155.220. There are conditions beyond the control and without the fault or negligence of the permittee.

155.300. With respect to coal to be mined for use in a synthetic fuel facility or specified major electric generating facility, the permittee will be deemed to have commenced coal mining and reclamation operations at the time that the construction of the synthetic fuel or generating facility is initiated.

155.400. Extensions of time granted by the Division under R645-300-155 will be specifically set forth in the permit, and notice of the extension will be made public by the Division.

160. Improvidently Issued Permits: Review Procedures.

161. Permit review. When the Division has reason to believe that it improvidently issued a coal mining and reclamation permit it will review the circumstances under which the permit was issued, using the criteria in R645-300-162. Where the Division finds that the permit was improvidently issued, it shall comply with R645-300-163.

162. Review criteria. The Division will find that a coal mining and reclamation permit was improvidently issued if:

162.100. Under the violations review criteria of the regulatory program at the time the permit was issued;

162.110. The Division should not have issued the permit because of an unabated violation or a delinquent penalty or fee; or

162.120. The permit was issued on the presumption that a notice of violation was in the process of being corrected to the satisfaction of the agency with jurisdiction over the violation, but a cessation order subsequently was issued; and

162.200. The violation, penalty or fee;

162.210. Remains unabated or delinquent; and

162.220. Is not the subject of a good faith appeal, or of an abatement plan or payment schedule with which the permittee or other person responsible is complying to the satisfaction of the responsible agency; and

162.300. Where the permittee was linked to the violation, penalty or fee through ownership or control, under the violations review criteria of the regulatory program at the time the permit was issued an ownership or control link between the permittee and the person responsible for the violation, penalty or fee still exists, or where the link was severed the permittee continues to be responsible for the violation, penalty or fee.

163. Remedial Measures.

When the Division, under R645-300-162 finds that because of an unabated violation or a delinquent penalty or fee a permit was improvidently issued it will use one or more of the following remedial measures:

163.100. Implement, with the cooperation of the permittee or other person responsible, and of the responsible agency, a plan for abatement of the violation or a schedule for payment of the penalty or fee;

163.200. Impose on the permit a condition requiring that in a reasonable period of time the permittee or other person responsible abate the violation or pay the penalty or fee;

163.300. Suspend the permit until the violation is abated or the penalty or fee is paid; or

163.400. Rescind the permit under R645-300-164.

164. Improvidently Issued Permits: Rescission procedures. When the Division under R645-300-163 elects to rescind an improvidently issued permit it will serve on the permittee a notice of proposed suspension and rescission which includes the reasons for the finding of the regulatory authority under R645-300-162 and states that:

164.100. Automatic suspension and rescissions. After a specified period of time not to exceed 90 days the permit automatically will become suspended, and not to exceed 90 days thereafter rescinded, unless within those periods the permittee submits proof, and the regulatory authority finds, that;

164.110. The finding of the Division under R645-300-162 was erroneous;

164.120. The permittee or other person responsible has abated the violation on which the finding was based, or paid the penalty or fee, to the satisfaction of the responsible agency;

164.130. The violation, penalty or fee is the subject of a good faith appeal, or of an abatement plan or payment schedule with which the permittee or other person responsible is complying to the satisfaction of the responsible agency; or

164.140. Since the finding was made, the permittee has severed any ownership or control link with the person responsible for, and does not continue to be responsible for, the violation, penalty or fee;

164.200. Cessation of operations. After permit suspension or rescission, the permittee shall cease all coal mining and reclamation operations under the permit, except for violation abatement and for reclamation and other environmental protection measures as required by the Division; and

164.300. Right to appeal. The permittee may file an appeal for administrative review of the notice under R645-300-200.

170. Final Compliance Review

After an application is approved, but before the permit is issued, the Division will reconsider its decision to approve the application based on the compliance review required by rule R645-300-132.100 and in light of any new information submitted under R645-301-112.900 and R645-301-113.400.

R645-300-200. Administrative and Judicial Review of Decisions on Permits.

The rules in R645-300-200 present the procedures for performing the entitled activities.

210. Administrative Review.

211. General. Within 30 days after an applicant or permittee is notified of the decision of the Division concerning a determination made under R645-106, an application for approval of exploration required under R645-200, a permit for coal mining and reclamation operations, a permit change, a permit renewal, or a transfer, assignment, or sale of permit rights, the applicant, permittee, or any person with an interest which is or may be adversely affected may request a hearing on the reasons for the decision, in accordance with R645-300-200.

212. Hearings.

212.100. The Board will start the administrative hearing within 30 days of such request. The hearing will be on the record and adjudicatory in nature. No person who presided at an informal conference under R645-300-123 will either preside at the hearing or participate in the decision following the hearing or administrative appeal.

212.200. The Board may, under such conditions as it prescribes, grant such temporary relief as it deems appropriate, pending final determination of the proceeding, if:

212.210. All parties to the proceeding have been notified and given an opportunity to be heard on a request for temporary relief;

212.220. The person requesting that relief shows that there is a substantial likelihood that he or she will prevail on the merits of the final determination of the proceeding;

212.230. The relief sought will not adversely affect the public health or safety, or cause significant, imminent environmental harm to land, air, or water resources; and

212.240. The relief sought is not the issuance of a permit where a permit has been denied, in whole or in part, by the Division except that continuation under an existing permit may be allowed where the operation has a valid permit issued under 40-10-11 of the Act.

212.300. The hearing will be conducted by the Board under the terms of the R641 Rules, including the requirement that there be no ex parte contact between the Board and representatives of parties appearing before the Board.

212.400. Within 30 days after the close of the record, the Board will issue and furnish the applicant and each person who participated in the hearing with the written findings of fact, conclusions of law, and order of the Board with respect to the appeal of the decision.

220. Judicial Review.

221. General. Any applicant or any person with an interest which is or may be adversely affected and who has participated in the administrative hearings as an objector may appeal as provided in R645-300-222 or R645-300- 223 if:

221.100. The applicant or person is aggrieved by the decision of the Board in the administrative hearing conducted pursuant to R645-300-200; or

221.200. The Board during administrative review under R645-300-200 fails to act within applicable time limits specified in the State Program.

222. State Program. Action of the Division or Board will be subject to judicial review by a court of competent jurisdiction, as provided for in the State Program, but the availability of such review will not be construed to limit the operation of the rights established in 40-10-21 of the Act.

223. Federal Lands Program. The action of the Division or Board is subject to judicial review by the United States District Court for the district in which the coal exploration or coal mining and reclamation operation is or would be located, in the time and manner provided for in Section 526(a)(2) and (b) of the Federal Act. The availability of such review will not be considered to limit the operations of rights established in Section 520 of the Federal Act.

KEY

reclamation, coal mines

Date of Enactment or Last Substantive Amendment

March 26, 2008

Notice of Continuation

March 7, 2007

Authorizing, Implemented, or Interpreted Law

40-10-1 et seq.


Rule converted into HTML by the Division of Administrative Rules.

For questions regarding the content or application of rules under Title R645, please contact the promulgating agency (Natural Resources; Oil, Gas and Mining; Coal). A list of agencies with links to their homepages is available at http://www.utah.gov/government/agencylist.html.

For questions about the rulemaking process, please contact the Division of Administrative (801-538-3764). Please Note: The Division of Administrative Rules is not able to answer questions about the content or application of these rules.


The HTML version of this rule is a convenience copy. This information is made available on the Internet as a public service. Please see this disclaimer about information available from www.rules.utah.gov.